Tystar 12
Non-MOS
Clean LTO LPCVD Furnace
(4” and
6”)
(tystar12)
Tystar12
is a 6” LPCVD tube, which is maintained for Non-MOS type, LTO / PSG
processes. This tube is capable of
processing both 4” and 6” wafers.
This
document has specific information about LPCVD Tystar12 furnace. This is our 6”
Non-MOS, general application tube dedicated to undoped low temperature oxide
(LTO) and phosphorous-doped low temperature oxide (PSG) processes. For general
information on LPCVD furnaces, please refer to Chapter 5.0 of
the lab manual, operation and pertinent information.
5.1
Non-MOS Tube: Tystar12 is a general/MEMS use type fabrication
furnace (Non-MOS).
5.2
LPCVD: Low pressure chemical vapor deposition
5.3
LTO: Low temperature silicon dioxide.
5.4
PSG: Phospho-silicate glass
5.5
Silane (SiH4): A gas used
in our LTO (doped & undoped) processes.
5.6
Phosphine (PH3): A gas used in our doped LTO process (PSG). Microlab
uses 50% PH3 and 50% SiH4
mixture for safety purpose.
5.7
Oxygen: A gas used
in LTO (doped & undoped) processes.
5.8
ROP: Remote-operation panel.
5.9
ALMACK: Alarm Acknowledge is a button used to proceed to
next step in recipe.
5.10
ABORT: This key can be used to abort the process. This is
commonly used for unloading the wafers, where users invoke the recipe again,
after run has been completed and properly vented. The tube will open for the
users to unload their wafers followed by abort to load the standby recipe, and
before leaving the area.
Machine Interlock
Messages
5.11 ANTLK: Above atmosphere interlock, no process gas can
flow (including N2).
5.12 NTLK: Below process pressure (2 Torr) interlock,
no process gas can flow.
5.13 DNTLK: Door interlock, door is not closed; no process
gas can flow.
5.14 GNTLK: Gate valve interlock, gate valve is not open,
no process gas can flow.
5.15 VNTLK: Vacuum interlock, pump problem, no process gas
can flow.
Pertinent
information can be found on the following sites:
7.1
Process monitoring test
section of the Microlab’s home page.
7.2
Problem and comments
section under equipment section of the wand.
7.3
Enable message for
Tystar12.
Tystar12 tube is assigned to LTO/PSG processes (undoped
and Phosphorous doped, respectively). There are three main recipes available on
the tool. This includes standard doped and undoped LTO as well as a variable
doped recipe. The latter allows for the user to change the value of phosphine
gas used in the recipe. These recipes
have an additional step (70), which sets the proper “K value” to speed up the
temp stabilization process.
8.1
Standard undoped LTO
process: The standard “12sultoa” recipe uses fixed amount of Silane and Oxygen,
no Phosphine to deposit low temperature silicon dioxide film at around 450ºC.
8.2
Standard fixed doped
LTO process (PSG): The standard “12sdltoa” recipe uses fixed amount of Silane,
Oxygen and Phosphine to deposit phospho-silicate glass film (PSG) at 450ºC.
8.3
Variable PSG process: The
variable “12vdltoa” recipe provides the flexibility to change the amount of
phosphine, silane and oxygen gases in the recipe, therefore, varying the amount
of phosphorous in the final film (PSG).
8.4
Deposited PSG film is
porous, therefore it is highly recommended to immediately anneal the film,
after deposition. This should prevent moisture absorption and possible
crystallization.
8.5
Do not attempt to run
any processes above 450ºC.
8.6
Available gases on this
tube are Silane (SiH4), Phosphine (PH3), Oxygen (O2),
Nitrogen (N2) and Nitrogen (N2 VAC) for pressure control.
9.2.1
Recipes
Tystar12 recipes are
residing on a dedicated diskette marked as “Tystar12 recipes”. These recipes have a standard format with
three pump and purge cycles before and after the deposition step. This is
designed to better control the film particles by keeping the tube cleaner.
There is also an additional temperature stabilization step incorporated into
these recipes, which is designed to optimize the ramp up time towards the
target deposition temperature”. Six recipes are available on this furnace which
are: standard undoped LTO; standard
doped LTO (PSG); standard variable LTO; standby; vent and purge recipes. The
vent and purge recipes are designed to speed up recovery process.
See Appendix 2 for more details on the available recipes.
|
12sultoa
recipe 12sdltoa
recipe 12vdltoa
recipe 12stnbya
recipe 12purge
recipe 12Vent
recipe |
Standard
undoped LTO, fixed SiH4 and O2. Standard
doped LTO (PSG), fixed SiH4, O2 and PH3. Variable
doped LTO (PSG), variable PH3, SiH4 and O2
gases. Standby
recipe should be loaded after you are done. Additional
recipe available to purge and vent the tube.* Additional
recipe available to vent the tube.* |
Note (*): The vent and purge recipes can
be used for quick vent or pump/purge cycles. The abort as you know, takes the
recipe back to its first step. This may take a long time for the tube to vent.
This is because the initial step bleeds only about one liter of nitrogen into
the tube, in which case it takes a long time to bring the tube to atmosphere.
This can be accomplished much faster by loading one of the two recipes noted
above, however take extreme care and make sure that you do not use the vent
recipe when harmful gases are present (abort at deposition step), load the
purge recipe instead. This can come handy when the abort has occurred, while
still in deposition step or if the origin of the abort sequence is not known
(did it abort at deposition step?).
9.2.2
Recipe
Modification and New Recipe Generation
As always,
modification to standard recipes is not allowed. Talk to process staff if you
need to develop special application recipes.
9.2.3
Recipe Loading
Type LO followed by recipe name and 12 to load the
recipe onto the tube from Tycom terminal. e.g. “LO 12sultoa 12”
9.2.4
Running Recipe
Once the recipe is loaded you can type RU followed by
tube number 12 or simply press run button on the ROC terminal.
9.2.5
Wafer Loading
Once
the boat is out, replace dummy wafers with your work wafers. There is a 20
minutes window available for this task. Once the 20 minutes elapses, the boat
loader will automatically go in. Do not worry, simply ALMACK through, cycle
back to “ boat unload” step and wait for the boat to come out. You have another 20 minutes to load your
wafers.
9.2.6
Unloading Wafers
Once
the process is completed the furnace will wait in flush and hold step. You will
need to ALMACK twice out of this step to vent the tube. You will need to run
the recipe again, so that the boat loader will bring the tube out. You will
then need to ALMACK to send the boat in and wait for the door to completely
close. You can then abort the process and load the standby recipe, before
signing off.
9.2.7
Standby recipe
(finishing up)
Once
your run is completed and your work wafers are out, you will need to load and
run the standby recipe “12stnbya”.
10.0
Troubleshooting
Guidelines
10.1 Failed
Leak Check
10.1.1 Check the machine status screen on the Tycom terminal
(type in “DI ST 12”).
10.1.1.1 If “GNTLK “
or “VNTLK” is ON, stop and report it as fault.
10.1.1.2 If “DNTLK” is
ON, vent the tube. Run the process again. Try this a couple of times, if
necessary. Report as fault, if still fails. There may be door sensor problems.
10.1.1.3
If no interlock is ON,
vent the tube wipe the door and the o-ring. Run the process again. If it still
fails, report it as fault.
10.2
No Process Gas
Flow
10.2.1
Check the machine
status screen on the Tycom terminal (type in “DI ST 12”).
10.2.1.1
If any interlock is ON,
report it as fault.
10.2.1.2
Check the appropriate
gas cylinder, if empty report as fault.
Appendix 1
|
12sultoa |
|
12sdltoa |
||||
|
Step --------- 01 05 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 |
Description -------------------------------------- Initialize & system
check Unload alarm Unload Boat Load on almack Load alarm Load boat Check door closed Pump1 Purge1 Pump2 Purge2 Pump3 Leak check Ramp to temp Set K Variable Temp stabilize Temp check Pump4 Process gas flows Pressure set (300 mTorr) Deposition step (PH3 =
0) Pump1 Purge1 Pump2 Purge2 Pump3 Purge3 Flush and hold Branch to backfill Loop back to flush &
hold Backfill-1 Backfill-2 End |
Time ----------- N/A 3 sec 10 min 20 min 3 sec 10 min 2 min 5 min 2 min 2 min 2 min 2 min 1 min 30 min 1 min 5 min 5 min 2 min 1 min 1 min Variable 2 min 2 min 2 min 2 min 2 min 2 min 1 hr 5 sec 1 sec 5 min 7 min N/A |
|
Step --------- 01 05 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 |
Description ---------------------------------------- Initialize & system
check Unload alarm Unload Boat Load on almack Load alarm Load boat Check door closed Pump1 Purge1 Pump2 Purge2 Pump3 Leak check Ramp to temp Set K Variable Temp stabilize Temp check Pump4 Process gas flows Pressure set (300 mTorr) Deposition step (PH3 =
fix) Pump1 Purge1 Pump2 Purge2 Pump3 Purge3 Flush and hold Branch to backfill Loop back to flush &
hold Backfill-1 Backfill-2 End |
Time ----------- N/A 3 sec 10 min 20 min 3 sec 10 min 2 min 5 min 2 min 2 min 2 min 2 min 1 min 30 min 1 min 5 min 5 min 2 min 1 min 1 min Variable 2 min 2 min 2 min 2 min 2 min 2 min 1 hr 5 sec 1 sec 5 min 7 min N/A |
|
12vdltoa |
|
12stnbya |
||||
|
Step --------- 01 05 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125 130 135 140 145 150 155 160 |
Description --------------------------------------------- Initialize & system
check Unload alarm Unload Boat Load on almack Load alarm Load boat Check door closed Pump1 Purge1 Pump2 Purge2 Pump3 Leak check Ramp to temp Set K Variable Temp stabilize Temp check Pump4 Process gas flows Pressure set (300 mTorr) Deposition step (PH3
= variable) Pump1 Purge1 Pump2 Purge2 Pump3 Purge3 Flush and hold Branch to backfill Loop back to flush &
hold Backfill-1 Backfill-2 End |
Time ----------- N/A 3 sec 10 min 20 min 3 sec 10 min 2 min 5 min 2 min 2 min 2 min 2 min 1 min 30 min 1 min 5 min 5 min 2 min 1 min 1 min Variable 2 min 2 min 2 min 2 min 2 min 2 min 1 hr 5 sec 1 sec 5 min 7 min N/A |
|
Step ------- 01 05 10 15 20 25 30 35 40 45 50 55 60 |
Description ------------------------------- Initialize Load Check door closed Short pump De-gas pump Hard pump Leak check Standby Branch to backfill-1 Loop back to standby Backfill-1 Backfill-2 end |
Time ------------ N/A 10 min 2 min 2 min 10 min 2 min 1 min 1 hr 5 sec 1 sec 5 min 7 min N/A |
Tystar 11-12 Study Guide
Be sure to know…
1.
Tystar 11 is MOS-clean; Tystar 12 is non-MOS clean.
2.
Unloading wafers and leaving the tube in standby.
3.
The meaning of the interlocks: DNTLK, GNTLK, VNTLK.
4.
Safety concerns if process is aborted in deposition step.
5.
Difference between recipes: 11SULTOA, 11SDLTOA, and 11VLTOA.
6.
How to set up a new recipe.
7.
If you ABORT before boat loading is complete.
8.
Unloading wafers after deposition.
9.
The meaning and purpose of pump and purge.
10.
Loading wafers: time limits and extending loading time.
11.
If the tube fails leak check.
12.
If there is no process gas flow.
Rev. 00 – 4/01, S. Parsa
Rev. 01 – 8/06, J. Chang – Minor revision of Section 5 and calibration
temperature.